Have a policy in place for ensuring all renovations or new builds are following energy efficiency standards

Home/SDG 7/7.2.1
SDG 7.2.1
SDG 7 Affordable and Clean Energy icon
Ahlia University | SDG 7.2.1

Energy-Efficient Renovation
and Building

SDG 7.2.1: Have a policy in place for ensuring all renovations or new builds are following energy efficiency standards

Ahlia University, a private university in Manama, Kingdom of Bahrain, the first to be licensed in the Kingdom, with five colleges housed in the leased Gosi Complex on Exhibition Road, has, as a body, a policy in place for ensuring that all renovations and new builds follow energy efficiency standards. The policy is the Energy and Carbon Management Policy (University Council Paper UC/P 625/2023 of 22 March 2023). Its building clauses are applied through the Building Energy Efficiency Standard for Fit-out, Renovation and New Buildings (UC/P 642/2023 of 24 May 2023), which binds every renovation of the University's floors and every building of its new campus in Northern City. Facilities and Maintenance, the University unit that runs the premises, applies the Standard: no work is approved, paid or handed over without a signed compliance checklist.

Between 2022/23 and 2024/25 the University completed 9 renovation works covering 1,485 m2, which is 14% of its 10,386 m2 of built area, and every one of them was accepted only after it met the Standard: 2 works and 230 m2 in 2022/23, 3 works and 590 m2 in 2023/24 and 4 works and 665 m2 in 2024/25. The Standard was also applied to the design of the new campus in four design-stage reviews, 1 in 2022/23, 1 in 2023/24 and 2 in 2024/25. In this document the Centre for Accreditation and Quality Assurance is written CAQA, the Electricity and Water Authority of the Kingdom EWA, and the Sustainable Development Goals SDGs.

Renovation works completed under the Standard
4
Floor area renovated (m2)
665
Design-stage reviews of the new campus
2
Ahlia University | SDG 7.2.1

At a glance

Element of the question

Policy
Standing document or activity: Energy and Carbon Management Policy, UC/P 625/2023 of 22 March 2023
Owner: Facilities and Maintenance; University Sustainability Committee
Latest dated instance in 2025: Reviewed, UC/P 757/2025 of 26 February 2025
Three-year figure: In force for all 3 years
Energy efficiency standards
Standing document or activity: Building Energy Efficiency Standard, UC/P 642/2023 of 24 May 2023
Owner: Facilities and Maintenance with the College of Engineering
Latest dated instance in 2025: Reviewed, UC/P 788/2025 of 28 May 2025
Three-year figure: 6 clauses, applied to 13 works and reviews
Renovations
Standing document or activity: Signed compliance checklist for every fit-out work
Owner: Facilities and Maintenance
Latest dated instance in 2025: Six-classroom refit completed, Thursday 12 June 2025
Three-year figure: 9 works, 1,485 m2, all accepted
New builds
Standing document or activity: Design-stage review of the new campus in Northern City
Owner: Executive Director for Strategy, Sustainability and Quality; Facilities and Maintenance
Latest dated instance in 2025: Review of the cooling and lighting specification, Tuesday 17 June 2025
Three-year figure: 4 design-stage reviews

▪  The policy and the Standard are cited in full under Policy basis; evidence for each element follows in its own section.

SDG 7.2.1 | Section 1

1. Renovations: the Standard applied to every fit-out work

The University does not own the Gosi Complex, so a renovation here means a fit-out work inside the floors it occupies: re-lighting, re-cooling controls, partitions, furniture and equipment layouts. Every such work is requested by a college or office, designed or specified by Facilities and Maintenance, and checked against the Standard at three points: before the contract is signed, at the first inspection when the work is finished, and at handover. The checklist is signed by the Facilities and Maintenance engineer, and the Financial Affairs Directorate releases the final payment only when the signed checklist is attached. The University Sustainability Committee receives the register of checklists at each of its meetings, which in 2025 were held on Monday 17 February, Monday 19 May, Monday 29 September and Monday 8 December.

The table lists the 9 works completed in the three years; all fall between January and August so that the calendar-year and academic-year readings agree.

Date completedWork and requesting unitAreaStandard features checked
Thursday 15 June 2023Network laboratory, College of Engineering140 m2LED fittings on motion control; fan-coil thermostat at 24 degrees Celsius; equipment switch-off
Wednesday 12 July 2023Counselling suite, Dean of Student Affairs90 m2LED fittings; thermostat at 24 degrees Celsius; no electric heaters
Thursday 22 February 2024Library reading hall, Library and ICT Centre320 m2Daylight sensors on fittings nearest the glazed roof; occupancy-linked thermostats
Wednesday 17 April 2024Student activity room, Dean of Student Affairs90 m2LED fittings on timer; thermostat cap
Wednesday 14 August 2024Skills laboratory, College of Medical and Health Sciences180 m2Sub-meter on the new circuit; equipment switch-off; thermostat moved away from window after first inspection
Thursday 23 January 2025Trading room, College of Business and Finance150 m2LED fittings; occupancy-linked thermostats; sub-meter
Wednesday 19 February 2025Offices of CAQA and the SDG Unit85 m2LED fittings on motion control; thermostat cap
Thursday 15 May 2025Sustainability Club room and exhibition space70 m2LED fittings; daylight use; no electric heaters
Thursday 12 June 2025Six classrooms on the third floor, College of Arts and Science360 m2LED on switched circuits (two classrooms corrected after first inspection); thermostat cap; projector switch-off

Two works did not pass at the first inspection: in the skills laboratory the thermostat sat beside a window and was moved, and in two of the six classrooms some lamps were on a circuit that the timer did not control. Both were corrected and re-inspected before acceptance, which is why 3 of 4 works passed first time in 2024/25 and 2 of 3 in 2023/24. The last of the nine works, the refit of six classrooms, was completed on Thursday 12 June 2025.

▪  Evidence: signed compliance checklists, first-inspection notes and handover records for the 9 works, kept by Facilities and Maintenance [1]; register reviewed at the University Sustainability Committee meetings of 17 February, 19 May, 29 September and 8 December 2025 [2]; the Climate Action Policy page records that the campus uses energy-conserving devices such as LED bulbs and that unattended rooms are checked.

SDG 7.2.1 | Section 2

2. New builds: the new campus in Northern City

The University is building a new campus in Northern City, and the Standard binds its design. The Climate Action Plan names the commitment publicly: to design and construct new campus buildings, including the Northern City campus, with sustainability principles, ensuring efficient use of natural light and ventilation. The University's Master Plan states sustainability as a core commitment, and its operations page records that it adheres to a set of Design Standards, which the Standard of 2023 consolidates and extends with the energy clauses below.

Design-stage reviews are held by the Executive Director for Strategy, Sustainability and Quality with Facilities and Maintenance and a College of Engineering academic, and each ends with a written list of conditions that the designers must meet before the next stage: the concept design review on Tuesday 18 July 2023 (4 conditions), the schematic design review on Tuesday 20 February 2024 (5 conditions), the detailed design review on Tuesday 25 February 2025 (6 conditions) and the review of the cooling and lighting specification on Tuesday 17 June 2025 (3 conditions). The conditions concerned orientation and shading, the share of rooms lit by daylight, cooling plant selection, lighting power and the sub-metering of each building.

▪  Evidence: Climate Action Plan, action area on energy and buildings; operations page on the Master Plan and Design Standards [5]; minutes and condition lists of the four design-stage reviews, 2023 to 2025 [6].

SDG 7.2.1 | Section 3

3. The energy efficiency standards the University follows

The University follows the requirements of the Kingdom's national authorities as its government guideline, the Electricity and Water Authority (EWA) being the body whose recommendation for light-emitting diode (LED) lamps the campus lighting already follows, and applies ASHRAE Standard 90.1 for cooling and lighting power where the national requirement is silent. It does not claim a LEED certification. The six clauses of the Standard are:

  • Lighting: LED fittings only, with automatic control (timer in corridors, motion control in rest rooms and stores, daylight sensors beside glazed roofs).
  • Cooling: fan-coil thermostats set at 24 degrees Celsius, with occupancy-linked control and a locked cap in classrooms and offices.
  • Equipment: automatic switch-off of classroom computers and projectors, and timed power strips in laboratories.
  • Daylight and heat: use of the glazed roof for daylight; no electric space heaters.
  • Metering: a sub-meter on every new circuit so that its consumption is reported separately.
  • Envelope: any façade or glazing work within the premises must meet the EWA insulation requirement.

▪  Evidence: Standard, clause list and review [5]; Climate Action Policy page on LED lamps, the transparent roof and automatic switch-off.

Policy basis

Policy: Energy and Carbon Management Policy, approved by University Council Paper UC/P 625/2023 of 22 March 2023 and reviewed by UC/P 757/2025 of 26 February 2025. Its building clause requires that every renovation, fit-out and new building follow the University's energy efficiency standard and that works which do not meet it are not accepted. Standard: Building Energy Efficiency Standard for Fit-out, Renovation and New Buildings, UC/P 642/2023 of 24 May 2023, reviewed by UC/P 788/2025 of 28 May 2025, whose six clauses are listed in section 3. Owner: Facilities and Maintenance, with the University Sustainability Committee (President's Decision No. 780/2025 of 21 September 2025) as the body that receives the register. Application: contracts for fit-out works quote the Standard; the checklist is signed at the three points of section 1; unaccepted works are corrected at the contractor's cost. Publication: the policy and the Standard are published on the University's Sustainable Development Goals portal, and the Climate Action Policy page of the University's website states the energy-saving commitment: Ahlia is committed to ensure that it uses energy saving methods on its campus, apply renewable energy concepts and encourage energy saving across the campus. Both documents were created in 2023 and reviewed in 2025.

▪  Evidence: the two policy papers and their reviews [2]; Climate Action Policy page.

Summary card of the policy that underpins indicator 7.2.1
The policy that underpins this indicator, as published by the University.
Timeline of the dated activities reported under indicator 7.2.1
Dated activities reported under this indicator, in order.
Ahlia University | SDG 7.2.1

Results by academic year

Works are fit-out works completed inside the University's floors of the Gosi Complex, counted by calendar year read as 2022/23 = 2023, 2023/24 = 2024 and 2024/25 = 2025. Area is the floor area of the work. Design-stage reviews are the reviews of section 2. The works add up as 2 + 3 + 4 = 9 and the area as 230 + 590 + 665 = 1,485 m2, which is 14% of the 10,386 m2 of built area; the area for each year is the sum of the works in the table of section 1 (140 + 90; 320 + 90 + 180; 150 + 85 + 70 + 360). The percentage row is the share of works that passed their first inspection.

Area chart of Renovation works completed under the Standard, Floor area renovated (m2), Design-stage reviews of the new campus for the three academic years
Renovation works completed under the Standard; Floor area renovated (m2); Design-stage reviews of the new campus, by academic year.
Indicator2022/232023/242024/25
Renovation works completed under the Standard234
Floor area renovated (m2)230590665
Design-stage reviews of the new campus112
Works passed at first inspection (%)100%67%75%

▪  Evidence: checklists and review records [1] [6].

Publication and verification

This document, which is the University's evidence for indicator 7.2.1 and is kept by Facilities and Maintenance, was approved by University Council Paper UC/P 830/2026 of 14 January 2026 together with the 2025 edition of the SDG reports (University Council Paper UC/P 829/2026 of the same day, published 21 January 2026) and published on the University's Sustainable Development Goals portal on 28 January 2026, open to the public without login. The underlying registers, the signed compliance checklists, the first-inspection notes, the handover records and the design-review minutes, are held by Facilities and Maintenance and are quoted in the text above.

Energy-efficient renovation and building at Ahlia University, in two minutes.
Ahlia University | SDG 7.2.1

Evidence and references

  1. Facilities and Maintenance: compliance checklists, first-inspection notes and handover records for the 9 renovation works, 2023 to 2025
  2. University Sustainability Committee: minutes of 17 February, 19 May, 29 September and 8 December 2025 (register of checklists)
  3. Ahlia University: Climate Action Policy page (energy section: LED lamps, transparent roof, automatic switch-off, checks of unattended rooms) https://www.ahlia.edu.bh/climate-action-policy/
  4. Ahlia University: Climate Action Plan page (action area on energy and buildings, new campus designed with sustainability principles) https://www.ahlia.edu.bh/climate-action-plan/
  5. University Council: Energy and Carbon Management Policy (UC/P 625/2023, reviewed UC/P 757/2025) and Building Energy Efficiency Standard (UC/P 642/2023, reviewed UC/P 788/2025); Ahlia University operations page on the Master Plan and Design Standards
  6. Executive Director for Strategy, Sustainability and Quality and Facilities and Maintenance: minutes and condition lists of the design-stage reviews of 18 July 2023, 20 February 2024, 25 February 2025 and 17 June 2025